Disley Tunnel

If you’d like to talk to us about a project, or anything else, we’d love to hear from you.
GET IN TOUCH

As part of the CP5 Renewals package, Force Contracting Completed an extensive drilling and grouting project at Disley tunnel under blockade conditions. Over the course of the 2016 Easter bank holiday weekend, FCS conducted essential repair works to the tunnel which was showing signs of ring separation. This involved pinning and grouting areas of the lining which had become hollow. This was done for a total of 501 m2.

PROJECT DETAILS

Client: J Murphy and Sons
Location: Disley, Cheshire
Year Completed: 2016